Manufacturing and Logistics Project Case

Manufacturer Multi Site Network Standard

Each plant had been built by a local contractor which left nine different network designs and no shared spare pool

Client Background

Who The Client Is

A contract manufacturer operating nine plants across four countries with no on site IT at six of them

Project Challenge

The Constraint That Mattered

Each plant had been built by a local contractor which left nine different network designs and no shared spare pool

Customer Pain Points

What Was Actually Going Wrong

  • A switch failure at a plant without on site IT meant a multi day production risk
  • No two plants used the same access model so spares could not be shared
  • Warehouse wireless coverage degraded whenever racking layouts changed

Our Solution

What We Did About It

A single plant template covering access switching branch routing and warehouse wireless was defined and shipped as a kit to each site with a matched on site spare.

Manufacturing And Process

How The Work Was Sequenced

  1. 1

    Existing designs audited and consolidated into one template

  2. 2

    Warehouse mounts selected against racking height and metal density

  3. 3

    Plant kits packed complete with a spare switch and spare access point per site

  4. 4

    Consignments released plant by plant against the local shutdown calendar

Supply Chain Coordination

How Supply Risk Was Removed

The template part numbers were held so replenishment and future plants draw on the same stock

Quality Control

What Was Checked On Every Unit

Every unit seal checked serial recorded and bench powered before the plant kit was sealed

Final Result

Outcome

Nine plants now run one template with a spare on site at each location

Customer Benefit

What Changed Afterwards

A switch failure is a swap performed by plant maintenance rather than a production incident

Related Products

Products Used in This Programme

J9150D Aruba switches

Aruba switches

J9150D

HPE J9150D - Aruba Transceiver Aruba 10G SFP+ LC SR 300m MMF XCVR:Aruba Aruba Campus Transceivers

Run a Programme Like This

Send the site count timeline and documentation requirement and we will map the supply plan against it

No forms No sign up Replies within one working day

FAQ

Questions About This Project

Could You Deliver a Programme Like This for Us

Yes. The shape transfers directly. What changes is the site count the change window rules and the documentation format your audit requires.

How Far Ahead Should We Start

For a multi wave programme start the availability and allocation conversation before the standard is fixed. That is the point where a discontinuation is cheap to design around.

What Held the Price Stable

Allocating programme quantity up front. Once stock is positioned against an agreed quantity the price is no longer exposed to spot movement.

Do You Pack per Site

Yes. Packing per site rather than per part number is normal on multi site work and is usually the single biggest saving on install labour.

How Were Serial Records Handled

Serial lists were issued per consignment in a format the client asset register could import directly rather than reconciled at the end.