Manufacturing and Logistics Project Case
Manufacturer Multi Site Network Standard
Each plant had been built by a local contractor which left nine different network designs and no shared spare pool
Client Background
Who The Client Is
A contract manufacturer operating nine plants across four countries with no on site IT at six of them
Project Challenge
The Constraint That Mattered
Each plant had been built by a local contractor which left nine different network designs and no shared spare pool
Customer Pain Points
What Was Actually Going Wrong
- A switch failure at a plant without on site IT meant a multi day production risk
- No two plants used the same access model so spares could not be shared
- Warehouse wireless coverage degraded whenever racking layouts changed
Our Solution
What We Did About It
A single plant template covering access switching branch routing and warehouse wireless was defined and shipped as a kit to each site with a matched on site spare.
Manufacturing And Process
How The Work Was Sequenced
- 1
Existing designs audited and consolidated into one template
- 2
Warehouse mounts selected against racking height and metal density
- 3
Plant kits packed complete with a spare switch and spare access point per site
- 4
Consignments released plant by plant against the local shutdown calendar
Supply Chain Coordination
How Supply Risk Was Removed
The template part numbers were held so replenishment and future plants draw on the same stock
Quality Control
What Was Checked On Every Unit
Every unit seal checked serial recorded and bench powered before the plant kit was sealed
Final Result
Outcome
Nine plants now run one template with a spare on site at each location
Customer Benefit
What Changed Afterwards
A switch failure is a swap performed by plant maintenance rather than a production incident
Related Products
Products Used in This Programme
Run a Programme Like This
Send the site count timeline and documentation requirement and we will map the supply plan against it
No forms No sign up Replies within one working day
FAQ
Questions About This Project
Could You Deliver a Programme Like This for Us
Yes. The shape transfers directly. What changes is the site count the change window rules and the documentation format your audit requires.
How Far Ahead Should We Start
For a multi wave programme start the availability and allocation conversation before the standard is fixed. That is the point where a discontinuation is cheap to design around.
What Held the Price Stable
Allocating programme quantity up front. Once stock is positioned against an agreed quantity the price is no longer exposed to spot movement.
Do You Pack per Site
Yes. Packing per site rather than per part number is normal on multi site work and is usually the single biggest saving on install labour.
How Were Serial Records Handled
Serial lists were issued per consignment in a format the client asset register could import directly rather than reconciled at the end.